This is how far your house is

Photo from 21 October

Site diary

  1. 21 OctoberFloor above the first storey poured, the formwork stays for ten days.
  2. 14 OctoberMasonry on the first storey done, window lintels set.
  3. 2 OctoberCrane moved, floor elements for house B delivered.
46%

Building site

Lindenhof apartments

Freiburg, Lindenstraße 14

Handover in June 2027

Trades

  • Earthworkscomplete
  • Slab and basementcomplete
  • Masonry72%
  • Floors55%
  • Roof0%
Next milestoneTopping outNov 28