Critical pathTask
| Task | Group | Start | End | Duration | Progress |
|---|---|---|---|---|---|
| Lease signed | Aug 3 | Aug 7 | 5 days | 100% | |
| Shop layout | Aug 10 | Aug 28 | 19 days | 100% | |
| Permit | Aug 31 | Sep 25 | 26 days | 100% | |
| Order oven | Aug 31 | Sep 4 | 5 days | 100% | |
| Fit-out | Sep 28 | Oct 23 | 26 days | 60% | |
| Hire the team | Sep 14 | Oct 16 | 33 days | 70% | |
| Install oven | Oct 26 | Oct 30 | 5 days | 0% | |
| Training | Nov 2 | Nov 6 | 5 days | 0% | |
| Opening day | Nov 9 | Milestone | No data |