57%on schedule
| Task | Group | Start | End | Duration | Progress |
|---|---|---|---|---|---|
| Kick-off and goals | Concept | Sep 1 | Sep 4 | 4 days | 100% |
| Audit and keywords | Concept | Sep 7 | Sep 18 | 12 days | 100% |
| Sitemap | Concept | Sep 14 | Sep 23 | 10 days | 100% |
| Wireframes | Design | Sep 21 | Oct 2 | 12 days | 100% |
| Visual design | Design | Sep 30 | Oct 16 | 17 days | 80% |
| Copy and photos | Design | Oct 5 | Oct 23 | 19 days | 55% |
| Build pages | Build | Oct 12 | Nov 6 | 26 days | 20% |
| Booking form | Build | Oct 26 | Nov 6 | 12 days | 0% |
| Device testing | Launch | Nov 9 | Nov 13 | 5 days | 0% |
| Go live | Launch | Nov 16 | Milestone | No data |