Website relaunch

On trackLena HoffmannDecember 4, 2026
68%complete
Tasks done
64 of 92
Days left
46
Dec 4
Budget used
62%
€29,800 of €48,000

Goal and key results

Make Café Mira bookable online before the winter season, without paying platform fees.

  • Table bookings per week through our own site

    64 / 120

    Started at 0

  • Mobile PageSpeed score

    88 / 95

    Started at 41

  • Share of orders without a platform

    19% / 35%

    Started at 8%

Updates

  1. Lena Hoffmann

    Project lead ·

    On track

    Design fully approved

    Café Mira signed off all 14 templates. From Monday Jonas builds the booking flow, Mia schedules the shoot of the new menu for Thursday.

    4 comments9 reactions
  2. Jonas Weber

    Development ·

    At risk

    Till access still missing

    The provider has not sent the API keys yet. Without them the test moves by a week.

    7 comments2 reactions

Upcoming milestones

  1. Oct28Bookings connected to the tillin 9 days · 2/5
  2. Nov13Beta for regularsin 25 days · 0/3
  3. Dec4Launchin 46 days · 0/3

Team

Client
Café Mira
Start
Aug 31, 2026
  • Lena HoffmannProject leadLead
  • Sofia KleinDesign
  • Jonas WeberDevelopment
  • Mia BrandtContent and photos
  • Noah BeckerSEO

Risks

  • Till provider delivers API keys late

    High

    Mitigation Café Mira calls the provider directly, if needed we launch with email bookings first.

    Owner Jonas Weber

  • New menu not final for the shoot

    Medium

    Mitigation Shoot the autumn dishes first.

    Owner Mia Brandt

  • Owner away for two weeks in November

    Low

    Mitigation Get beta approvals before she leaves.

    Owner Lena Hoffmann