How it works

Six steps to your own power

  1. 01First call

    20 min
    We
    We ask about your use, the roof and your wishes and estimate the size.
    You
    Have a power bill at hand.
  2. 02Site visit

    1 hour
    We
    We measure the roof and check the meter cabinet and cable routes.
    You
    Access to the attic and the basement.
  3. 03Offer

    5 days
    We
    A fixed price with a yield forecast and a layout for every module.
  4. 04Registration

    2 to 4 weeks
    We
    We register the system with the grid operator and sort out the funding.
    You
    Sign the application.
  5. 05Installation

    1 to 2 days
    We
    Scaffolding, modules, inverter and battery, by the evening everything is wired.
  6. 06Commissioning

    1 day
    We
    Meter swap with the grid operator, a test run and the documents.
    You
    Set up the app and celebrate the first kilowatt hour.